- With reference to dry-docking:
(a) state what is meant by the critical period on settling onto the dock blocks;(3)
(b) explain the reasons why this period is considered critical;(5)
(c) state how the danger is reduced.(2)
CHIEF ENGINEER Unit 16 Dry Docking Procedure Q1
8. (a) State the procedures and safety checks that should be undertaken prior to flooding a dry dock.(9)
(b) State who is responsible for signing the authority for a Flood Certificate.(1)
CHIEF ENGINEER Unit 16 Dry Docking Procedure Q2
8.(a) Describe the basic construction and operation of a Vertical Ship Lift.(6)
(b) List TWO advantages and TWO disadvantages of a Vertical Ship Lift.(4)