Aux 2 Unit 13 Crane, lifting equipment Flashcards

Aux 2 Unit 13 Crane, lifting equipment

Which of the following is NOT typically included on a Proof Load Test certificate?

B) Weather conditions during the test

What must be ensured before a crane can be used for deploying and recovering loads on a vessel?

B) It must pass a thorough inspection and load test, proving compliance with international safety standards

Which of the following is a key part of the inspection routine for lifting gear?

B) Checking for structural integrity and visible damage, such as cracks and deformations

What should be inspected to ensure the safe operation of lifting gear?

B) The presence of any loose or missing bolts, worn-out chains, or damaged ropes

What information should be included when recording inspection and test results of lifting equipment?

B) The date, type of inspection/test, findings, and any corrective actions taken

Why is it important to check the SWL (Safe Working Load) markings during an inspection?

B) To verify that the markings are clearly visible and have not worn off

According to present maritime regulations, which standard must a crane comply with before being used on a vessel?

C) International Labour Organization (ILO) Convention 152

What information should be included when recording inspection and test results of lifting equipment?

B) The date, type of inspection/test, findings, and any corrective actions taken

Where should the results of lifting equipment inspections and tests be recorded?

B) A dedicated Lifting Gear Register or inspection record

Why is it important to include the test load applied on a Proof Load Test certificate?

B) To document that the crane was tested beyond its Safe Working Load (SWL) for safety verification

Which of the following regulations specifically address the use of lifting appliances on board vessels?

C) ILO Convention 152 on Occupational Safety and Health in Dock Work

Which of the following pieces of information must be included on a Proof Load Test certificate for a crane?

B) The test load applied, the date of the test, and the name of the certifying authority

What is the maximum time period between tests of lifting equipment to confirm its load-bearing capacity?

B) Every 12 months

What is the maximum recommended time period between inspections of lifting equipment on a vessel?

C) Every 12 months
1 / 14